Road Construction Near Monmouth Mall Six Months Behind Schedule
DOT says utility relocation to blame.
Construction at the intersection of Routes 35 and 36 in Eatontown has hit a speed bump.
The New Jersey Department of Transportation, which is running the massive project near Monmouth Mall, said this week that work there will take six months longer than originally projected. The project will realign Route 35, reconfigure traffic at its intersection with Route 36 and add sidewalks.
According to DOT spokesman Timothy Greeley, the department recently authorized a schedule extension, which will push the project out to January 2013.
The DOT reported only minor delays in October due to utility relocation and said its contractor was rearranging the construction schedule to keep the project moving, even as it waited on utility companies to move their lines.
The new year brings a renewed timeline and the DOT rep said that the relocation of water, electric, gas and telephone lines are to blame for the six-month extension to construction.
"It would be unfair to specify one company," Greeley said. "More than a normal job, utility relocation played a big role."
According to Greeley, DeFino Contracting has finished the first stage of construction and is progressing through the final elements of the second stage of construction. Currently the old Route 35 southbound lanes at the intersection (old alignment) are being excavated and construction of new median, sidewalks and associated drainage work will continue through the winter, provided the weather cooperates.
Route 35 northbound will remain in the existing alignment until the third stage of construction begins in early spring. During this stage the contractor will shift Route 35 northbound to the new alignment, make improvements to the Route 36 westbound ramp to Route 35 northbound, construct a new loop ramp to connect Route 36 eastbound traffic to Route 35 northbound and complete final median, sidewalk and surface pavement work throughout the project limits.
One of the goals of the project is to ease congestion at the Route 36 and Wyckoff Road area. By the end of the project, Route 36 eastbound traffic that now heads down Wyckoff Road (by TD Bank and the All Seasons Diner) en route to Route 35 north (by Toys R Us), will be redirected. Eventually drivers, exiting the parkway for example, will head east on Route 36 and will pass Wyckoff Road to take a new jughandle (by Sawa), which will put them onto Route 35 north (by Ashley Furniture).
Edie Memmott
9:32 am on Monday, January 9, 2012
Too bad for the delay, but with the extra storms in 2011, uitlity companies are stretched on staff....too bad new jobs could not have been created to keep this project "on time".....the public needs it done and it is already was a long time coming....
Bob English
5:27 pm on Monday, January 9, 2012
Traffic does seem to be moving a lot better on 35 south approaching the 36 intersection. For a long time it was taking 2-3 light changes to get across 36 even in the middle of the day.
Ken Karmazyn
8:31 pm on Monday, January 9, 2012
By the time the dust has cleared I am sure that we will all find that this "new and improved intersection" will not ease the traffic at all. This intersection should have been eliminated with a RT 35 overpass of RT 36. That would have been money better spent.
S Talarico
6:24 am on Tuesday, January 10, 2012
Bring back the circle!
Joey Bagdano
9:03 am on Wednesday, January 11, 2012
Been by there 14 times and have yet to see anyone working. I do notice that its reminiscent of Baghdad circa 2009-11.
john dennis
7:37 pm on Friday, March 30, 2012
I live in long branch and as of yesterday march 29 in 6 mo I've seen one lone man trying to finish the job ALL BY HIMSELF such a pity, but on the bright side at least theres one job still going.
Herky
8:52 pm on Friday, March 30, 2012
Ken Karmazyn: YES!! It worked very well at the junction of US Rte 1 & State RTE # 130 in North Brunswick, also at Rte #9 and Ernston Road in Sayreville.. But you must under stand the State road engineers never do it right the first 6 times. It's known as JOB Security.. Where would they be working if it was done right the first time.. This is an example why the STATE TRANSPORTTAION FUND IS BROKE.. Don't take it personal , it's just business as usual in the Garden State!